About the project

The project is construction of Carrier line (HDPE Pipes 315 mm, Steel Pipes 18 inch) of the desalination plant for the limited quantity south of Deir El Balah with a length of 17 km. The Carrier line extends from the desalination plant to the western areas of Khan Younis and Rafah. The plant is expected to produce 6,000 cubic meters of desalinated water in Khan Younis & Rafah, where the desalinated water will be mixed with the water of the reservoir in both reservoirs and then pumped into the networks and the estimated number of beneficiaries of the project about 75 thousand people.

Client

United Nations Children’s Fund (UNICEF)

Owner

 CMWU Coastal Municipalities Water Utility

Finance

United Nations Children’s Fund (UNICEF)

Supervision

Universal Group / Artelia JV

Company’s Status

Prime Contractor

Location

South Gaza

Year

2014-2015